On 11/17/26, the Loudoun County Board of Supervisors in Virginia adopted a resolution (“Resolution”) imposing a pause of up to 12 months on its final decisions on certain data center and electrical substation applications. The decision matters well beyond Loudoun County. The area around Ashburn is one of the world’s most important data center hubs. The Resolution introduces a significant permitting delay for projects that require approval by the Board of Supervisors and highlights the growing importance of local land-use and energy policies for U.S. data center development, reflecting the outcome of the the Midterm elections.

What is “paused”?

The November 3 midterm elections added political momentum to the Board’s initiative. Voters supported restrictions or additional requirements in 40 of 41 local data center ballot measures nationwide, reinforcing the political pressure on local officials to respond to concerns about electricity costs, land use and environmental impacts. The pause in Loudoun County applies to certain legislative applications, including rezonings and special exceptions for data centers and substations. It is intended to give the County time to complete the second phase of its data center standards and zoning updates. It is not a blanket suspension of permitting and not meant to be a “moratorium” on data centers:

  • Developers may continue to submit applications.
  • Applications may continue through review by the Planning Commission.
  • The pause affects the Board’s final decisions on covered applications.
  • Grid-reliability substations and certain Route 28 District zoning applications are exempt.

The Resolution applies retroactively from September 15, 2026. The 12-month period is calculated separately for each application, by reference to its consideration by the Planning Commission.

Key legal implications

County Attorney Rogers considers the time-limited pause lawful under Virginia law. He distinguishes it from an indefinite moratorium, which he considers impermissible. The County relies on the statutory framework requiring action on covered legislative applications within a reasonable time, not exceeding 12 months. The County’s legal position does not eliminate litigation risk. Opponents see real threat of legal challenges, and industry representatives have argued that the pause operates as a moratorium in practice. For developers, operators of data centers and investors, the principal issues include:

  • Statutory deadlines: Whether the County applies the 12-month limit correctly to each application, and whether delays in practice comply with the applicable statutory and local requirements.
  • Vested rights and reliance: Whether a project has acquired protected rights under Virginia law will depend on its permitting status, applicable approvals and the developer’s investments and reliance. Filing an application alone does not necessarily establish vested rights.
  • Grandfathered projects: Certain applications filed before February 12, 2025, remain eligible for treatment under prior zoning rules pursuant to a 2025 transition provision. The Board indefinitely postponed a proposal to repeal those protections in October after County officials warned of substantial litigation exposure. This process requires further observation and analysis.
  • Project claims and disputes: Applicants may challenge the County’s application of the pause, particularly where delays affect existing approvals, contractual commitments, financing or substantial project investments.

Related trend: Restrictions on nondisclosure agreements

The pause in Loudoun County is part of a broader push for transparency in local data center approvals. Developers have often asked local officials to sign nondisclosure agreements (“NDAs”) during site selection. A 2025 review found NDAs in 25 of 31 Virginia localities with existing or proposed data centers. Critics say these agreements keep residents from learning about a project’s effects on land, water and electricity rates until late in the approval process. Developers respond that confidentiality protects commercially sensitive information during site selection and land acquisition. Nonetheless, Microsoft, Amazon and Google have separately announced that they have ended or are phasing out the use of NDAs in data center projects.  Lawmakers are increasingly siding with the critics of NDAs for data center development:

  • Enacted state law: Delaware’s Senate Bill 312, signed on August 26, 2026, bars state agencies, counties and municipalities from entering NDAs that would keep the public from accessing information about large-scale data center development (facilities using 100 MW or more). Florida’s Senate Bill 484 takes a narrower approach: it requires public disclosure of data center development agreements once a 12-month exemption period ends.
  • Executive action: Virginia Governor Spanberger’s data center Executive Order 22 of September 18, 2026 bans NDAs for new projects, which is directly relevant to Loudoun County. In Pennsylvania, Governor Shapiro’s August 18, 2026 Executive Order 2026-05 prohibits state agencies under his jurisdiction from entering NDAs on data center projects.
  • Pending state bills: On October 22, 2026, the New Jersey Senate voted 38–0 to pass S.4304, which would ban agreements that hide information about data center development. Similar bills are pending in Michigan (SB 1049), Ohio (HB 695), New York (S.10708) and Pennsylvania. The Michigan and Ohio bills would impose fines of up to $1,000 and authorize the state Attorney General to bring enforcement actions. The Ohio bill would also void any contract entered in violation. One Pennsylvania bill (HB 2359) would make the sales tax exemption for data center equipment conditional on the absence of government NDAs.
  • Federal and local initiatives: On September 24, 2026, a bipartisan group of House members introduced the No Secrets for Data Centers Act (H.R. 10570). The bill would invalidate NDAs that federal, state and local officials sign to conceal details of data center projects. It would also bar government incentives that are conditioned on confidentiality, while preserving protection for legitimate trade secrets. At the local level, the Climate Mayors model local law recommends that cities prohibit NDAs with data center developers.

For developers, these measures can make confidentiality commitments from public officials unenforceable or void. They can also put tax incentives at risk and push sensitive project information into the public record earlier than planned. Developers will likely need to rely on public-records exemptions for trade secrets, rather than on contractual NDAs with officials.

What should U.S. businesses do now?

The Resolution could set the stage for similar measures elsewhere. Data center developers, operators, investors and infrastructure suppliers with projects in Loudoun County and beyond. should:

  • Identify whether pending projects require legislative approval by the Board or are proceeding through administrative permitting.
  • Review each application’s procedural status and applicable decision deadline.
  • Assess existing approvals, grandfathering eligibility and potential vested-rights arguments.
  • Revisit project schedules, financing, construction commitments and contractual milestones to account for possible delays.
  • Review existing and proposed NDAs with public officials for enforceability under new state laws and executive orders and plan for earlier public disclosure of project information.

The Resolution is a local measure, not a nationwide prohibition on data center development. But it is a clear signal that local zoning decisions, electricity infrastructure and community opposition can materially affect project timelines and investment risk—even in established data center markets.